Site I, The Mill, Catteshall Road, Godalming

appeal 6006517·Waverley·21 September 2026dismissed
Decision
dismissed, 21 September 2026
Decided by
Planning Inspector: J Heppell
Authority
Waverley (South East)
Appeal reference
6006517
Application reference
WA/2023/02694
Procedure
written representations
Development
Building of 9 flats with parking, in lieu of an extant 2002 permission for an office building
Homes
9
Site context
inside settlement, conservation area, flood zone 2, flood zone 3, PDL
Green Belt
No
Housing land supply
1.28 years
Framework applied
August 2026 NPPF
Determinative policies
S4, DP3(3), F7(2), HO7
Development plan policies
Waverley LPP1 2018 RE3, TD1, NE1, NE2, CC1, CC4, LRC1, Waverley LPP2 2023 DM1, DM4, DM5, DM7, Godalming & Farncombe NP 2019 GOD5
Main issues
character and appearance of ASVI; flood risk; SNCI; living conditions

Summary

Nine flats on a partly previously developed riverside site in Godalming, within the settlement but partly in the Area of Strategic Visual Importance (ASVI) and Flood Zones 2/3, in place of an extant office permission from 2002. Dismissed despite a 1.28-year supply. The inspector applied S4 and found the substantial housing benefits "substantially outweighed" because two national policies directing refusal were engaged: DP3(3) (design/context) and F7(2) (increased flood risk elsewhere). Inadequate play space also counted.

Issues and findings

Planning balance

S4: "Although none of the situations listed in the policy apply to the proposal, I am nonetheless required to consider whether the benefits … would be substantially outweighed" (DL ¶44). HO7 substantial weight at 1.28 years (DL ¶45); L2 effective use, social/economic benefits (DL ¶46). "National decision-making Policy DP3 directs refusal … whilst Policy F7 directs refusal where flood risk would be increased elsewhere. I conclude that the benefits of approving development would be substantially outweighed by the adverse effects" (DL ¶50).

What made the difference

Two "should be refused" national policies were failed. The flood point turned on an engineering detail: compensatory storage was designed against the office fallback rather than the existing site, and the fallback carried little weight because it had not been built in over 20 years. On design, moving the building closer to the river than the permitted office, within a protected open river corridor, was decisive. Full level-for-level compensation against the existing site, plus a building set back where the office would have been, would probably have tipped the balance given the 1.28-year supply.

Transferable points

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
DP3faildominant building close to the River Wey in an Area of Strategic Visual Importance; DP3(3) directs refusal absent clear justification (DL 23, 47, 50)
F7(2)failno level-for-level compensatory flood storage (compensation measured against office fallback) and bank reclamation may lose storage — increases flood risk elsewhere; F7(2) directs refusal (DL 29-31, 48, 50)
F5passsequential test accepted in absence of Council challenge (applied via PPG) (DL 26)
F6failexception test part 1 passed (wider sustainability benefits, 1.28-yr supply); part 2 failed (not safe without increasing flood risk elsewhere); safe access accepted despite EA (DL 27-31)
HC3failno on-site Local Area for Play where none within 100 m (DL 38, 49)
HE6harmCouncil found "moderate degree of less than substantial harm" to CA outweighed by housing; inspector did not disagree; treated as neutral (DL 22, 46)
N6passnot named; negligible effect on SNCI; no adverse effect on Wey Valley Meadows SSSI (DL 35-37)
HO7benefitsubstantial1.28-yr supply; smaller units meeting identified needs (DL 45)
L2(1)(b)benefitbetter use of partly PDL, sustainably located site; folded into overall substantial weight (DL 46, 50)
S4failno S4(2) circumstance said to apply, yet benefits substantially outweighed given DP3 and F7 refusal directions (DL 43-44, 50)

Key facts

Sources

This note is one of the decisions behind the NPPF 2026 Navigator, which shows how each Framework test has been applied across all the decisions in the database. Also available as Markdown.