Morgan and Morecambe Offshore Wind Farms Transmission Assets (DCO)

application EN020032·Fylde / South Ribble / Blackpool / Preston (Lancashire)·14 September 2026approved
Decision
approved, 14 September 2026
Decided by
Secretary of State: Baroness Curran for SoS DESNZ; ExA D Cliff, J Gorst, R Morgan, M Rokicka
Authority
Fylde / South Ribble / Blackpool / Preston (Lancashire) (North West)
Application reference
EN020032
Procedure
inquiry
Development
DCO for offshore and onshore transmission assets for two consented offshore wind farms - export cables, landfall, onshore cables, two onshore substations in the Green Belt and 400 kV connection to Penwortham
Site context
green belt, open countryside
Green Belt
Yes (grey belt not argued)
Framework applied
December 2024 NPPF (transitional)
Determinative policies
NPS EN-1 5.11.37, GB6(2)
Development plan policies
Fylde Local Plan to 2032 GD2, GD3, GD7, ENV5
Main issues
Green Belt VSC; aviation safety; habitats; onshore ecology; compulsory acquisition

Summary

This was a DCO for the onshore and offshore transmission assets of two consented Irish Sea wind farms. It included two new onshore substations in the Lancashire Green Belt, connecting to the National Grid at Penwortham. The Examining Authority recommended refusal. The Secretary of State for Energy Security and Net Zero granted consent on 14 September 2026, after post-examination information resolved the bird-strike risk to BAE Warton and the habitats (SPA integrity) issue. It is the first Secretary of State planning decision found that expressly acknowledges the August 2026 NPPF. The letter says the new Framework changes nothing, and it applies the 2024 wording.

Issues and findings

Planning balance

The decision was under PA 2008 s104, on NPS EN-1, EN-3 and EN-5 (2024) with the NPPF as an "important and relevant" consideration. A Green Belt VSC balance under EN-1 ¶5.11.37 was run "against all harms". On one side: renewable energy need (substantial). On the other: Green Belt (substantial), onshore ecology (significant), heritage and landscape (moderate each), and several limited harms. The benefits "clearly outweigh" the harms, so the critical national priority presumption did not need to be relied on (DL ¶7.18).

What made the difference

The ExA's refusal rested on two harms that fell away after the examination: BAE's bird-strike objection and the SPA integrity finding. Once they were resolved, substantial renewable-energy weight carried the Green Belt VSC test for two substations that had no alternative site outside the Green Belt. The 2026 Framework made no difference, because the NPS governs and the Secretary of State expressly kept the 2024 references. For Framework-reading purposes the letter mainly shows that NSIP decisions in the transition are not engaging the new policy codes.

Transferable points

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
GB6(2)harmsubstantialtwo onshore substations are inappropriate development causing significant harm to openness and undermining purposes (a) and (c); assessed under 2024 NPPF paras 153/160 and NPS EN-1 5.11.37 (DL 4.111-4.113, 7.12, 7.14)
W3benefitsubstantialurgent need for renewable generating capacity; VSC "now clearly outweigh" Green Belt and other harm (DL 7.4, 7.14-7.16) - assessed under NPS, not under W3 by name
N6harmsignificantresidual significant adverse effects on non-breeding waders and Mill Brook Valley BHS, limited BNG; SoS departs from ExA's great weight and AEoI conclusion on Ribble and Alt Estuaries SPA (DL 7.7, 7.15)
HE6harmmoderateresidual moderate adverse effects on buried archaeology; benefits outweigh with "clear and convincing justification" (DL 7.8, 7.13)
DP3harmlimitedgood design partially met (DL 7.11)

Key facts

Sources

This note is one of the decisions behind the NPPF 2026 Navigator, which shows how each Framework test has been applied across all the decisions in the database. Also available as Markdown.