Prow Park Business Village, Treloggan Industrial Estate, Newquay

appeal 6002971·Cornwall·27 August 2026dismissed
Decision
dismissed, 27 August 2026
Decided by
Planning Inspector: Lewis Condé
Authority
Cornwall (South West)
Appeal reference
6002971
Application reference
PA25/08160
Procedure
written representations
Development
Refusal to discharge conditions 3 (landscaping), 4 (biodiversity management plan) and 5 (drainage) on a parking and container storage use
Site context
settlement edge
Green Belt
No
Framework applied
August 2026 NPPF
Determinative policies
DM6
Main issues
discharge of conditions

Summary

Appeal against refusal to discharge three conditions. The landscaping details lacked specifications, the off-site biodiversity gain was not legally secured, and the drainage as built did not match the approved plan. Dismissed. The new Framework made "no changes material to this appeal" (DL ¶5).

What made the difference

Off-site BNG "must be secured by a planning obligation or conservation covenant" (DL ¶15), and a condition requiring compliance with an approved drawing cannot be met by an "equally or more effective" alternative (DL ¶21). Costs applications from both sides were the subject of separate decisions (DL ¶2), so the costs-refused tag is unconfirmed.

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
DM6faildetails did not satisfy conditions; off-site BNG at Perranporth Airport not secured by a s106 or conservation covenant; drainage not built to the approved drawing (DL 11-22)

Key facts

Sources