Land east of Gwel An Syllan, Truthwall Lane, Truthwall (St Just)

appeal 6003055·Cornwall·9 September 2026dismissed
Decision
dismissed, 9 September 2026
Decided by
Planning Inspector: C Butcher
Authority
Cornwall (South West)
Appeal reference
6003055
Application reference
PA25/04202
Procedure
written representations
Development
Permission in principle for 1-9 dwellings
Homes
9
Site context
settlement edge, conservation area, national landscape, open countryside
Green Belt
No
Housing land supply
3.8 years
Framework applied
August 2026 NPPF
Determinative policies
HE6(4), N4(1), S5(1), S4(2)(a)(ii)
Development plan policies
Cornwall Local Plan Strategic Policies 2010-2030 Policies 1, 2, 3, 12, 23, 24, Climate Emergency DPD 2023 C1, St Just in Penwith NP 2021-2030 AH6, AD1, AD8, Chief Planning Officer's Advice Note on Infill/Rounding Off 2017
Main issues
suitability of location; land use and amount for PIP; rounding off; conservation area; National Landscape

Summary

Permission in principle for 1–9 dwellings on a field opposite a short row of cottages in the very small village of Truthwall, near St Just. The site lies within a conservation area, the Cornwall National Landscape and a World Heritage Site. Dismissed. Nine dwellings would be disproportionate and would not be "rounding off". The scheme would erode the village's transition to countryside, harming the conservation area and the NL. That harm substantially outweighs the moderate benefits, both under S5 and, in the alternative, under S4. The Council's supply was 3.8 years.

Issues and findings

Planning balance

First the HE6(4) heritage balance, which failed because the benefits were moderate (DL ¶17). Then S5(1), where the harm to the CA and NL "would substantially outweigh" the benefits (DL ¶27), with an alternative S4(1) and S4(2)(a)(ii) route reaching the same answer (DL ¶28). The benefits were up to nine homes, possible affordable units, reasonable public transport and economic activity, "moderate in nature when considered in combination" (DL ¶25). The development plan conflict was not outweighed (DL ¶30).

What made the difference

The site's role as the undeveloped edge giving a small historic village its rural transition. That role counted twice, as conservation-area harm and as NL harm, with statutory and N4 substantial weight on both. The PIP format also hurt the appellant: a 1–9 range is judged at nine, and nine was out of scale for the village. A PIP for one or two dwellings might have fared better on "amount", but the heritage and NL objection to any built form on the site would probably remain.

Transferable points

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
HE6(4)harmsubstantialless-than-substantial ("harm" under HE6(1)) to Botallack and Truthwall CA - loss of village-to-countryside transition; moderate public benefits do not outweigh (DL 14-17)
N4(1)conflictsubstantialCornwall NL; CA harm "would also extend to the scenic beauty of the NL"; LURA 2023 duty to further purposes (DL 18-19)
World Heritage SiteneutralCornwall and West Devon Mining Landscape WHS (St Just district) - smallholding link too uncertain to find harm to OUV (DL 20-21)
S5(1)(j)(i)passoutside settlement boundary but well-related to built form; 3.8-yr supply - "could therefore be said to be met" (DL 26-27)
S5(1)failharm to CA and NL "would substantially outweigh the benefits" (DL 27)
S4(1)failalternative finding - even if within the settlement, harm substantially outweighs benefits (DL 28)
S4(2)(a)(ii)failalternative finding - substantial adverse impact on the NL (N4) (DL 28)
HO7benefitinspector unsure HO7 is triggered; even with substantial weight the outcome is the same (DL 29)
L3neutralharm means no efficient use of land - "Given the identified harm, I do not find that the proposal would result in an efficient use of land" (DL 25)
CLP Policy 3 (rounding off)conflict9 dwellings disproportionate to very small village; lane and Cornish hedge form logical boundary; not rounding off (DL 8-12)

Key facts

Sources

This note is one of the decisions behind the NPPF 2026 Navigator, which shows how each Framework test has been applied across all the decisions in the database. Also available as Markdown.