Land west of 103 Tonbridge Road, Hildenborough (PIP, 5 to 7 homes)

appeal 6010459·Tonbridge and Malling·29 September 2026allowed
Decision
allowed, 29 September 2026
Decided by
Planning Inspector: C Shearing
Authority
Tonbridge and Malling (South East)
Appeal reference
6010459
Application reference
25/01693/PIP
Procedure
written representations
Development
Permission in principle for between 5 and 7 dwellings on Green Belt land partly within the Hildenborough Conservation Area
Homes
7
Site context
green belt, settlement edge, conservation area, listed building setting, TPO
Green Belt
Yes (grey belt accepted)
Housing land supply
2.89 years
Framework applied
August 2026 NPPF
Determinative policies
GB7(1)(g), HE6(4), S5(5), HO7
Development plan policies
Tonbridge and Malling Core Strategy 2007 CP3, CP12, CP14, CP24, Managing Development and the Environment DPD 2010 SQ1
Main issues
heritage (Hildenborough Conservation Area); whether inappropriate development in the Green Belt

Summary

Permission in principle for 5 to 7 homes on Green Belt land at the edge of Hildenborough, partly inside the conservation area, was allowed. The access would break a protected hedgerow that defines the conservation area's edge, causing harm at the lower end of the scale. The inspector ran HE6(4) first and found the homes and economic benefits outweighed that harm. The site was grey belt, GB7(1)(g) was met (with the Golden Rules assumed to be deliverable at the next stage), and the S5(5) balance favoured approval.

Issues and findings

Planning balance

HE6(4) first: public benefits outweigh low-level harm (DL ¶19). Then S5(5), applying S5(2): no "should be refused" policy fails, and "Overall the benefits would not be substantially outweighed by the adverse effects, when assessed against the national decision-making policies in the Framework" (DL ¶29). The presumption is "a consideration of sufficient weight to determine the appeal other than in accordance with the development plan" (DL ¶29).

What made the difference

Three things. The heritage harm was confined to one break in a hedgerow that already has other breaks nearby, so it sat at the bottom of the scale. A supply of 2.89 years gave a handful of homes substantial weight. And the permission-in-principle stage let the inspector assume the Golden Rules contributions could be secured later, without evidence. On a full application the GB8 contributions and the access detail would have had to be shown.

Transferable points

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
HE6(3)harmconsiderableharm to the Hildenborough Conservation Area "at the lower end of the scale of harm"; the access would break the uninterrupted, TPO-protected hedgerow on the southern side of Tonbridge Road (DL 10-11, 13, 18)
HE6(1)harmsubstantialsubstantial weight to the asset's conservation "irrespective of the level of harm" (DL 18)
HE6(4)pass5 to 7 homes (substantial weight) and economic benefits (moderate weight) outweigh the harm; balance run separately, before the Green Belt and S5(5) steps (DL 19)
HE9harmmapped: HE9 not cited; northern part of the site is in the conservation area; s72(1) and s66(1) duties applied to a permission in principle (DL 8)
HE7neutralmapped: HE7 not cited; no harm to the non-designated Foxbush Historic Park and Garden or other non-designated assets; no harm to the settings of Grade II Pembroke Lodge and Woodside Cottage (DL 15-17)
AnnexB:grey-beltpassdoes not strongly contribute to purposes (a), (b) or (d); site does not adjoin a large built-up area, form a substantial part of a gap between towns, or relate to a historic town; Arup Green Belt Assessment does not alter this (DL 20)
GB7(1)(g)(i)passwould not fundamentally undermine the purposes of the remaining Green Belt across the plan area (DL 20)
GB7(1)(g)(ii)passevidenced unmet need; 2.89 years supply (officer report) and HDT "well below 75%" (appellant) (DL 19-20)
GB7(1)(g)(iii)passpassed in one sentence as "very close to services and facilities in Hildenborough as well as bus links"; no distances, route or frequencies given; TR3 not cited (DL 20)
GB7(1)(g)(iv)passsite exceeds 0.5 ha so is major development under Annex B; no evidence on the Golden Rules, but obligations cannot be secured at PIP stage, so GB8 contributions assumed capable of being met at technical details stage (DL 21)
GB8passassumed, not evidenced or secured; deferred to the technical details consent stage (DL 21)
S5(5)passnot inappropriate, so approve unless benefits substantially outweighed, applying S5(2); benefits not substantially outweighed (DL 28-29)
S5(2)not-engagedno failure of a national policy that says proposals should be refused (DL 29)
HO7benefitsubstantialsubstantial weight "whether that be 5 or 7 homes", given acknowledged unmet need (DL 19, 29)
E2benefitmoderatemapped: E2 not cited; construction and occupier spending (DL 19, 29)
Transitional(2)conflictlimitedSQ1 (local distinctiveness) not consistent with the Framework because it has no balancing exercise; CP12 and CP14 (development within rural settlement confines) inconsistent with the Framework and not delivering enough homes; conflict with each given limited weight, citing Annex A (DL 14, 23)