The Triangle, 5-17 Hammersmith Grove

appeal 6010549·Hammersmith and Fulham·23 September 2026allowed
Decision
allowed, 23 September 2026
Decided by
Planning Inspector: D Cleary
Authority
Hammersmith and Fulham (London)
Appeal reference
6010549
Application reference
2025/02533/FUL
Procedure
written representations
Development
Glazed single storey entrance extension over existing steps with handrail and new side steps to office building (interim works before Phase 2 redevelopment)
Site context
inside settlement
Green Belt
No
Framework applied
August 2026 NPPF
Determinative policies
s38(6)
Development plan policies
London Plan 2021 D5, H&F Planning Guidance SPD DA1, DA6
Main issues
safe and inclusive access

Summary

A glazed entrance foyer over stepped access to an office building, pending a consented redevelopment. Allowed. An existing step-free rear entrance, a conditioned access-improvement package and the interim nature of the works made the lack of level access at the front acceptable. The Framework's "format has altered" but the considerations had "not fundamentally changed" (DL ¶3).

What made the difference

Proportionality. These were interim works, with an alternative level entrance secured by an access management plan condition.

Policy findings

Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.

PolicyFindingWeightNote
D5 (London Plan)accordno level access at front but existing level rear entrance plus secured access-improvement package; interim works before Phase 2 (DL 7-12)
DP3(2)(f)passsafe and inclusive access — no Framework policy cited; code mapped by harvester