- Decision
- approved, 2 September 2026
- Decided by
- Council planning committee: Maldon District Planning Committee
- Authority
- Maldon (East of England)
- Application reference
- 26/00018/FULM
- Procedure
- committee
- Development
- Hybrid — full permission for 170 dwellings, outline for up to 190 dwellings (40% affordable), retention of employment land, open space, bridleway
- Homes
- 360
- Site context
- open countryside, settlement edge
- Green Belt
- No
- Housing land supply
- 4.1 years
- Framework applied
- August 2026 NPPF
- Determinative policies
- S5(1)(j)(i), S3, TR3, HO7
- Development plan policies
- Maldon LDP 2017 S2, S6 (Burnham-on-Crouch strategic allocations), E1, H1
- Main issues
- S5(1)(j); landscape; highways phasing
Summary
Up to 360 homes as a westward extension of an allocated Burnham-on-Crouch strategic site that is under construction. Approved under S5(1)(j): 4.1-year supply, physically well related, infrastructure secured. Officers: "The identified adverse effects do not substantially outweigh the significant housing and affordable-housing benefits" (Report ¶3.1.17).
Issues and findings
- S5(1)(j). "The proposal relates directly to the existing strategic allocation and addresses an evidenced housing-supply shortfall in a location physically well related to Burnham-on-Crouch and capable of being supported by the necessary infrastructure" (¶3.1.11).
- Location. The station is about 1.6 km away, a 20-minute walk (¶5.1.16). Some amenity routes are "towards the upper end of a convenient walking journey" (¶5.1.15).
- Deliverability was treated as part of the benefit: Phase 1 from April 2027 "ensuring that this housing would be delivered within the 5-Year Housing Land Supply (5YHLS) period" (¶3.1.12).
Transferable points
- An extension of an allocation under construction is a natural S5(1)(j) "well-related" case (¶3.1.11).
- Delivery within the five-year period was used to add weight to the housing benefit (¶3.1.12).
Policy findings
Policy codes are those of the National Planning Policy Framework (August 2026) unless a development plan is named.
| Policy | Finding | Weight | Note |
|---|---|---|---|
| S5(1)(j)(i) | pass | adjoins and is accessed through allocated Burnham-on-Crouch West scheme under construction; 4.1-year supply; infrastructure via S106/S278 | |
| TR3 | pass | Burnham station c.1.6 km (20 min walk); several amenities 'towards the upper end of a convenient walking journey'; railway crossing safety contribution | |
| HO7 | benefit | substantial | homes deliverable within five-year period (Phase 1 from April 2027); 40% affordable vs 30% policy |
Key facts
- Extension of an allocated strategic site under construction by the same developer
- Independent landscape consultant found harm acceptable because the site is enclosed to north and west
- Highway works phased; members required Kitts Hill/B1012 works before first occupation